Widening and Strengthening of existing S/L, I/L, & D/L to 2 Lane with PS from Km 256/455 to 256/503, 256/820 to 256/960, 265/760 to 266/010, 266/010 to 266/800, 270/975 to 271/055, 276/460 to 276/560, 276/560 to 276/700, 276/700 to 277/480, 285/780 to 288/290, 288/290 to 291/050 and construction of 3 Nos. of Bypass from Km 266/800 to 267/300, 270/025 to 270/975, & 284/700 to 285/780 on NH-53 under NHO in Annual Plan 2022-23 for the State of Odisha.
Original Cost
₹174 Cr
Baseline estimate
Revised Cost
₹174 Cr
Latest approved cost
Expenditure
₹62 Cr
Spent to date
Utilization
35.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹112 Cr
Budget left
Budget Utilization
35.8%Spent
₹62 Cr
Remaining
₹112 Cr
Total
₹174 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
29/12/2027
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹174 Cr — no cost escalation recorded.
Expenditure stands at ₹62 Cr, which is 35.8% of the revised project cost.
Remaining budget: ₹112 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening and Strengthening of existing S/L, I/L, & D/L to 2 Lane with PS from Km 256/455 to 256/503, 256/820 to 256/960, 265/760 to 266/010, 266/010 to 266/800, 270/975 to 271/055, 276/460 to 276/560, 276/560 to 276/700, 276/700 to 277/480, 285/780 to 288/290, 288/290 to 291/050 and construction of 3 Nos. of Bypass from Km 266/800 to 267/300, 270/025 to 270/975, & 284/700 to 285/780 on NH-53 under NHO in Annual Plan 2022-23 for the State of Odisha. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹174.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening and Strengthening of existing S/L, I/L, & D/L to 2 Lane with PS from Km"?
- Widening and Strengthening of existing S/L, I/L, & D/L to 2 Lane with PS from Km 256/455 to 256/503, 256/820 to 256/960, 265/760 to 266/010, 266/010 to 266/800, 270/975 to 271/055, 276/460 to 276/560, 276/560 to 276/700, 276/700 to 277/480, 285/780 to 288/290, 288/290 to 291/050 and construction of 3 Nos. of Bypass from Km 266/800 to 267/300, 270/025 to 270/975, & 284/700 to 285/780 on NH-53 under NHO in Annual Plan 2022-23 for the State of Odisha. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹174 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹174 Cr has not been significantly revised. Expenditure: ₹62 Cr (35.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening and Strengthening of existing S/L, I/L, & D/L to 2 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617918. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening and Strengthening of existing S/L, I/L, & D/L to 2 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.