Original Cost
₹423 Cr
Baseline estimate
Revised Cost
₹423 Cr
Latest approved cost
Expenditure
₹160 Cr
Spent to date
Utilization
37.8%
Of revised budget
Cost Status
+0.1%
+₹0 Cr increase
Remaining
₹263 Cr
Budget left
Spent
₹160 Cr
Remaining
₹263 Cr
Total
₹423 Cr
Original Cost
₹423 Cr
Revised Cost
₹423 Cr
Increase
+₹0 Cr
Escalation
+0.1%
Project Approved
Construction / Implementation
Original End Date
18/12/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹0 Cr (0.1%) from the original estimate of ₹423 Cr.
Expenditure stands at ₹160 Cr, which is 37.8% of the revised project cost.
Remaining budget: ₹263 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.