Roads & HighwaysIPM · Central Project +13.4% overrun#617928

Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav Chokdi-Satlasana to to Vrundavan Chokdi, Kheralu on NH-58 in the State of Gujarat.

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹171 CrUtilization: 88.3%Overrun: +₹20 Cr

Original Cost

₹151 Cr

Baseline estimate

+13% overrun

Revised Cost

₹171 Cr

Latest approved cost

Expenditure

₹151 Cr

Spent to date

Utilization

88.3%

Of revised budget

Escalated

Cost Status

+13.4%

+₹20 Cr increase

Remaining

₹20 Cr

Budget left

Budget Utilization

88.3%
0%25%50%75%100%

Spent

₹151 Cr

Remaining

₹20 Cr

Total

₹171 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹151 Cr

Revised Cost

₹171 Cr

Increase

+₹20 Cr

Escalation

+13.4%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/03/2026

Revised Completion

20/08/2026

Completed

Project Details

Project Code617928
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹151 Cr
Revised Cost₹171 Cr
Expenditure₹151 Cr
Original End Date14/03/2026
Revised Date20/08/2026

Project Intelligence

Cost has increased by ₹20 Cr (13.4%) from the original estimate of ₹151 Cr.

Expenditure stands at ₹151 Cr, which is 88.3% of the revised project cost.

Remaining budget: ₹20 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav Chokdi-Satlasana to to Vrundavan Chokdi, Kheralu on NH-58 in the State of Gujarat. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹151.00 Cr, later revised to ₹171.27 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav Chokdi-Satlasana to t"?
Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav Chokdi-Satlasana to to Vrundavan Chokdi, Kheralu on NH-58 in the State of Gujarat. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹151 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹151 Cr and has been revised to ₹171 Cr — a cost overrun of +13.4%. Expenditure to date: ₹151 Cr (88.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav C is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617928. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav C is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.