Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav Chokdi-Satlasana to to Vrundavan Chokdi, Kheralu on NH-58 in the State of Gujarat.
Original Cost
₹151 Cr
Baseline estimate
Revised Cost
₹171 Cr
Latest approved cost
Expenditure
₹151 Cr
Spent to date
Utilization
88.3%
Of revised budget
Cost Status
+13.4%
+₹20 Cr increase
Remaining
₹20 Cr
Budget left
Budget Utilization
88.3%Spent
₹151 Cr
Remaining
₹20 Cr
Total
₹171 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹151 Cr
Revised Cost
₹171 Cr
Increase
+₹20 Cr
Escalation
+13.4%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
14/03/2026
Revised Completion
20/08/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹20 Cr (13.4%) from the original estimate of ₹151 Cr.
Expenditure stands at ₹151 Cr, which is 88.3% of the revised project cost.
Remaining budget: ₹20 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav Chokdi-Satlasana to to Vrundavan Chokdi, Kheralu on NH-58 in the State of Gujarat. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹151.00 Cr, later revised to ₹171.27 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav Chokdi-Satlasana to t"?
- Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav Chokdi-Satlasana to to Vrundavan Chokdi, Kheralu on NH-58 in the State of Gujarat. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹151 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹151 Cr and has been revised to ₹171 Cr — a cost overrun of +13.4%. Expenditure to date: ₹151 Cr (88.3% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav C is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617928. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Widening 2 lane to 4-lane from KM 92/320 to Km 115/320 Vav C is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.