RailwaysIPM · Central Project#611974

Western Railway- Samakhiali-Gandhidham Quadrupiling 53 km PB34/CR/2023-24

Ministry of RailwaysGujarat
Revised Cost: ₹1430 CrUtilization: 55.7%

Original Cost

₹1430 Cr

Baseline estimate

On budget

Revised Cost

₹1430 Cr

Latest approved cost

Expenditure

₹796 Cr

Spent to date

Utilization

55.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹634 Cr

Budget left

Budget Utilization

55.7%
0%25%50%75%100%

Spent

₹796 Cr

Remaining

₹634 Cr

Total

₹1430 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/12/2026

Revised Completion

31/12/2027

Completed

Project Details

Project Code611974
SectorRailways
MinistryMinistry of Railways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹1430 Cr
Revised Cost₹1430 Cr
Expenditure₹796 Cr
Original End Date30/12/2026
Revised Date31/12/2027

Project Intelligence

Project is within original budget of ₹1430 Cr — no cost escalation recorded.

Expenditure stands at ₹796 Cr, which is 55.7% of the revised project cost.

Remaining budget: ₹634 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Western Railway- Samakhiali-Gandhidham Quadrupiling 53 km PB34/CR/2023-24 is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1430.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Western Railway- Samakhiali-Gandhidham Quadrupiling 53 km PB34/CR/2023-24"?
Western Railway- Samakhiali-Gandhidham Quadrupiling 53 km PB34/CR/2023-24 is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Gujarat. Original cost: ₹1430 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1430 Cr has not been significantly revised. Expenditure: ₹796 Cr (55.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Western Railway- Samakhiali-Gandhidham Quadrupiling 53 km PB is under the Ministry of Railways in the Railways sector. Project code: 611974. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Western Railway- Samakhiali-Gandhidham Quadrupiling 53 km PB is one of several Bihar projects tracked under the Railways sector on the IPM system.