Original Cost
₹51.1K Cr
Baseline estimate
Revised Cost
₹1.24L Cr
Latest approved cost
Expenditure
₹1.25L Cr
Spent to date
Utilization
100.5%
Of revised budget
Cost Status
+142.7%
+₹72.9K Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹1.25L Cr
Remaining
₹0 Cr
Total
₹1.24L Cr
Original Cost
₹51.1K Cr
Revised Cost
₹1.24L Cr
Increase
+₹72.9K Cr
Escalation
+142.7%
Project Approved
Construction / Implementation
Original End Date
31/03/2022
Revised Completion
31/12/2025
Completed
Mega infrastructure project worth ₹1.24L Cr — among the largest central projects in Rajasthan.
Cost has increased by ₹72.9K Cr (142.7%) from the original estimate of ₹51.1K Cr.
Expenditure stands at ₹1.25L Cr, which is 100.5% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.