Wardha - Yavatmal Nanded Railway Line Project
Original Cost
₹3445 Cr
Baseline estimate
Revised Cost
₹4031 Cr
Latest approved cost
Expenditure
₹4053 Cr
Spent to date
Utilization
100.6%
Of revised budget
Cost Status
+17.0%
+₹586 Cr increase
Remaining
₹0 Cr
Budget left
Budget Utilization
100.6%Spent
₹4053 Cr
Remaining
₹0 Cr
Total
₹4031 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹3445 Cr
Revised Cost
₹4031 Cr
Increase
+₹586 Cr
Escalation
+17.0%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2026
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹586 Cr (17.0%) from the original estimate of ₹3445 Cr.
Expenditure stands at ₹4053 Cr, which is 100.6% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Wardha - Yavatmal Nanded Railway Line Project is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹3445.00 Cr, later revised to ₹4030.69 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Wardha - Yavatmal Nanded Railway Line Project"?
- Wardha - Yavatmal Nanded Railway Line Project is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹3445 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹3445 Cr and has been revised to ₹4031 Cr — a cost overrun of +17%. Expenditure to date: ₹4053 Cr (100.6% of revised cost). Data as of 2026-07.
- QWhich ministry is responsible for this project?
- Wardha - Yavatmal Nanded Railway Line Project is under the Ministry of Railways in the Railways sector. Project code: 705497. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Wardha - Yavatmal Nanded Railway Line Project is one of several Bihar projects tracked under the Railways sector on the IPM system.