Original Cost
₹3445 Cr
Baseline estimate
Revised Cost
₹4031 Cr
Latest approved cost
Expenditure
₹4043 Cr
Spent to date
Utilization
100.3%
Of revised budget
Cost Status
+17.0%
+₹586 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹4043 Cr
Remaining
₹0 Cr
Total
₹4031 Cr
Original Cost
₹3445 Cr
Revised Cost
₹4031 Cr
Increase
+₹586 Cr
Escalation
+17.0%
Project Approved
Construction / Implementation
Original End Date
31/12/2026
Revised Completion
Completed
Cost has increased by ₹586 Cr (17.0%) from the original estimate of ₹3445 Cr.
Expenditure stands at ₹4043 Cr, which is 100.3% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.