Wardha - Yavatmal Nanded Railway Line Project

Ministry of RailwaysMaharashtra
Revised Cost: ₹4031 CrUtilization: 100.6%Overrun: +₹586 Cr

Original Cost

₹3445 Cr

Baseline estimate

+17% overrun

Revised Cost

₹4031 Cr

Latest approved cost

Expenditure

₹4053 Cr

Spent to date

Utilization

100.6%

Of revised budget

Escalated

Cost Status

+17.0%

+₹586 Cr increase

Remaining

₹0 Cr

Budget left

Budget Utilization

100.6%
0%25%50%75%100%

Spent

₹4053 Cr

Remaining

₹0 Cr

Total

₹4031 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹3445 Cr

Revised Cost

₹4031 Cr

Increase

+₹586 Cr

Escalation

+17.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2026

Revised Completion

Completed

Project Details

Project Code705497
SectorRailways
MinistryMinistry of Railways
StateMaharashtra
Data Month2026-07

Financial Summary

Original Cost₹3445 Cr
Revised Cost₹4031 Cr
Expenditure₹4053 Cr
Original End Date31/12/2026
Revised DateN/A

Project Intelligence

Cost has increased by ₹586 Cr (17.0%) from the original estimate of ₹3445 Cr.

Expenditure stands at ₹4053 Cr, which is 100.6% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Wardha - Yavatmal Nanded Railway Line Project is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹3445.00 Cr, later revised to ₹4030.69 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Wardha - Yavatmal Nanded Railway Line Project"?
Wardha - Yavatmal Nanded Railway Line Project is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹3445 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹3445 Cr and has been revised to ₹4031 Cr — a cost overrun of +17%. Expenditure to date: ₹4053 Cr (100.6% of revised cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
Wardha - Yavatmal Nanded Railway Line Project is under the Ministry of Railways in the Railways sector. Project code: 705497. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Wardha - Yavatmal Nanded Railway Line Project is one of several Bihar projects tracked under the Railways sector on the IPM system.