RailwaysIPM · Central Project +87.2% overrun#705505

Wardha-Nagpur - 4th line 78.70 km

Ministry of RailwaysMaharashtra
Revised Cost: ₹1195 CrUtilization: 91.7%Overrun: +₹557 Cr

Original Cost

₹638 Cr

Baseline estimate

+87% overrun

Revised Cost

₹1195 Cr

Latest approved cost

Expenditure

₹1095 Cr

Spent to date

Utilization

91.7%

Of revised budget

Escalated

Cost Status

+87.2%

+₹557 Cr increase

Remaining

₹100 Cr

Budget left

Budget Utilization

91.7%
0%25%50%75%100%

Spent

₹1095 Cr

Remaining

₹100 Cr

Total

₹1195 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹638 Cr

Revised Cost

₹1195 Cr

Increase

+₹557 Cr

Escalation

+87.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2025

Revised Completion

31/10/2026

Completed

Project Details

Project Code705505
SectorRailways
MinistryMinistry of Railways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹638 Cr
Revised Cost₹1195 Cr
Expenditure₹1095 Cr
Original End Date31/12/2025
Revised Date31/10/2026

Project Intelligence

Cost has increased by ₹557 Cr (87.2%) from the original estimate of ₹638 Cr.

Expenditure stands at ₹1095 Cr, which is 91.7% of the revised project cost.

Remaining budget: ₹100 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Wardha-Nagpur - 4th line 78.70 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹638.00 Cr, later revised to ₹1194.59 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Wardha-Nagpur - 4th line 78.70 km"?
Wardha-Nagpur - 4th line 78.70 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹638 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹638 Cr and has been revised to ₹1195 Cr — a cost overrun of +87.2%. Expenditure to date: ₹1095 Cr (91.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Wardha-Nagpur - 4th line 78.70 km is under the Ministry of Railways in the Railways sector. Project code: 705505. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Wardha-Nagpur - 4th line 78.70 km is one of several Bihar projects tracked under the Railways sector on the IPM system.