Original Cost
₹4803 Cr
Baseline estimate
Revised Cost
₹4803 Cr
Latest approved cost
Expenditure
₹2979 Cr
Spent to date
Utilization
62.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1824 Cr
Budget left
Spent
₹2979 Cr
Remaining
₹1824 Cr
Total
₹4803 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
Completed
Project is within original budget of ₹4803 Cr — no cost escalation recorded.
Expenditure stands at ₹2979 Cr, which is 62.0% of the revised project cost.
Remaining budget: ₹1824 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.