Vijayawada19.50 km & Kazipet10.65 km -Byepass line
Original Cost
₹647 Cr
Baseline estimate
Revised Cost
₹827 Cr
Latest approved cost
Expenditure
₹711 Cr
Spent to date
Utilization
85.9%
Of revised budget
Cost Status
+27.9%
+₹180 Cr increase
Remaining
₹116 Cr
Budget left
Budget Utilization
85.9%Spent
₹711 Cr
Remaining
₹116 Cr
Total
₹827 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹647 Cr
Revised Cost
₹827 Cr
Increase
+₹180 Cr
Escalation
+27.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
12/01/2025
Revised Completion
31/12/2025
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹180 Cr (27.9%) from the original estimate of ₹647 Cr.
Expenditure stands at ₹711 Cr, which is 85.9% of the revised project cost.
Remaining budget: ₹116 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Vijayawada19.50 km & Kazipet10.65 km -Byepass line is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹647.00 Cr, later revised to ₹827.46 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Vijayawada19.50 km & Kazipet10.65 km -Byepass line"?
- Vijayawada19.50 km & Kazipet10.65 km -Byepass line is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Telangana. Original cost: ₹647 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹647 Cr and has been revised to ₹827 Cr — a cost overrun of +27.9%. Expenditure to date: ₹711 Cr (85.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Vijayawada19.50 km & Kazipet10.65 km -Byepass line is under the Ministry of Railways in the Railways sector. Project code: 705632. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Vijayawada19.50 km & Kazipet10.65 km -Byepass line is one of several Bihar projects tracked under the Railways sector on the IPM system.