RailwaysIPM · Central Project +27.9% overrun#705632

Vijayawada19.50 km & Kazipet10.65 km -Byepass line

Ministry of RailwaysTelangana
Revised Cost: ₹827 CrUtilization: 85.9%Overrun: +₹180 Cr

Original Cost

₹647 Cr

Baseline estimate

+28% overrun

Revised Cost

₹827 Cr

Latest approved cost

Expenditure

₹711 Cr

Spent to date

Utilization

85.9%

Of revised budget

Escalated

Cost Status

+27.9%

+₹180 Cr increase

Remaining

₹116 Cr

Budget left

Budget Utilization

85.9%
0%25%50%75%100%

Spent

₹711 Cr

Remaining

₹116 Cr

Total

₹827 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹647 Cr

Revised Cost

₹827 Cr

Increase

+₹180 Cr

Escalation

+27.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

12/01/2025

Revised Completion

31/12/2025

Completed

Project Details

Project Code705632
SectorRailways
MinistryMinistry of Railways
StateTelangana
Data Month2026-08

Financial Summary

Original Cost₹647 Cr
Revised Cost₹827 Cr
Expenditure₹711 Cr
Original End Date12/01/2025
Revised Date31/12/2025

Project Intelligence

Cost has increased by ₹180 Cr (27.9%) from the original estimate of ₹647 Cr.

Expenditure stands at ₹711 Cr, which is 85.9% of the revised project cost.

Remaining budget: ₹116 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Vijayawada19.50 km & Kazipet10.65 km -Byepass line is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹647.00 Cr, later revised to ₹827.46 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Vijayawada19.50 km & Kazipet10.65 km -Byepass line"?
Vijayawada19.50 km & Kazipet10.65 km -Byepass line is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Telangana. Original cost: ₹647 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹647 Cr and has been revised to ₹827 Cr — a cost overrun of +27.9%. Expenditure to date: ₹711 Cr (85.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Vijayawada19.50 km & Kazipet10.65 km -Byepass line is under the Ministry of Railways in the Railways sector. Project code: 705632. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Vijayawada19.50 km & Kazipet10.65 km -Byepass line is one of several Bihar projects tracked under the Railways sector on the IPM system.