Original Cost
₹1910 Cr
Baseline estimate
Revised Cost
₹2652 Cr
Latest approved cost
Expenditure
₹672 Cr
Spent to date
Utilization
25.4%
Of revised budget
Cost Status
+38.9%
+₹742 Cr increase
Remaining
₹1980 Cr
Budget left
Spent
₹672 Cr
Remaining
₹1980 Cr
Total
₹2652 Cr
Original Cost
₹1910 Cr
Revised Cost
₹2652 Cr
Increase
+₹742 Cr
Escalation
+38.9%
Project Approved
Construction / Implementation
Original End Date
21/03/2024
Revised Completion
31/12/2027
Completed
Cost has increased by ₹742 Cr (38.9%) from the original estimate of ₹1910 Cr.
Expenditure stands at ₹672 Cr, which is 25.4% of the revised project cost.
Remaining budget: ₹1980 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.