Original Cost
₹2059 Cr
Baseline estimate
Revised Cost
₹2325 Cr
Latest approved cost
Expenditure
₹630 Cr
Spent to date
Utilization
27.1%
Of revised budget
Cost Status
+12.9%
+₹266 Cr increase
Remaining
₹1695 Cr
Budget left
Spent
₹630 Cr
Remaining
₹1695 Cr
Total
₹2325 Cr
Original Cost
₹2059 Cr
Revised Cost
₹2325 Cr
Increase
+₹266 Cr
Escalation
+12.9%
Project Approved
Construction / Implementation
Original End Date
11/05/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹266 Cr (12.9%) from the original estimate of ₹2059 Cr.
Expenditure stands at ₹630 Cr, which is 27.1% of the revised project cost.
Remaining budget: ₹1695 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.