Vadodara Mumbai Expressway Phase II - Pkg XIII [Km. 26.582 to Km. 50.700] Shirsad - Masvan
Original Cost
₹3537 Cr
Baseline estimate
Revised Cost
₹4680 Cr
Latest approved cost
Expenditure
₹1987 Cr
Spent to date
Utilization
42.5%
Of revised budget
Cost Status
+32.3%
+₹1143 Cr increase
Remaining
₹2693 Cr
Budget left
Budget Utilization
42.5%Spent
₹1987 Cr
Remaining
₹2693 Cr
Total
₹4680 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹3537 Cr
Revised Cost
₹4680 Cr
Increase
+₹1143 Cr
Escalation
+32.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
08/02/2024
Revised Completion
31/08/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹1143 Cr (32.3%) from the original estimate of ₹3537 Cr.
Expenditure stands at ₹1987 Cr, which is 42.5% of the revised project cost.
Remaining budget: ₹2693 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Vadodara Mumbai Expressway Phase II - Pkg XIII [Km. 26.582 to Km. 50.700] Shirsad - Masvan is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹3537.00 Cr, later revised to ₹4679.54 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Vadodara Mumbai Expressway Phase II - Pkg XIII [Km. 26.582 to Km. 50.700] Shirsa"?
- Vadodara Mumbai Expressway Phase II - Pkg XIII [Km. 26.582 to Km. 50.700] Shirsad - Masvan is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹3537 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹3537 Cr and has been revised to ₹4680 Cr — a cost overrun of +32.3%. Expenditure to date: ₹1987 Cr (42.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Vadodara Mumbai Expressway Phase II - Pkg XIII [Km. 26.582 t is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618469. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Vadodara Mumbai Expressway Phase II - Pkg XIII [Km. 26.582 t is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.