Vadodara Mumbai Expressway Karvad - Jujuwa from Km. 128.000 to Km. 154.600 Phase-I Package-IX
Original Cost
₹2594 Cr
Baseline estimate
Revised Cost
₹2587 Cr
Latest approved cost
Expenditure
₹238 Cr
Spent to date
Utilization
9.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2349 Cr
Budget left
Budget Utilization
9.2%Spent
₹238 Cr
Remaining
₹2349 Cr
Total
₹2587 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
13/10/2025
Revised Completion
31/07/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹2594 Cr — no cost escalation recorded.
Expenditure stands at ₹238 Cr, which is 9.2% of the revised project cost.
Remaining budget: ₹2349 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Vadodara Mumbai Expressway Karvad - Jujuwa from Km. 128.000 to Km. 154.600 Phase-I Package-IX is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2594.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Vadodara Mumbai Expressway Karvad - Jujuwa from Km. 128.000 to Km. 154.600 Phase"?
- Vadodara Mumbai Expressway Karvad - Jujuwa from Km. 128.000 to Km. 154.600 Phase-I Package-IX is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹2594 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2594 Cr and has been revised to ₹2587 Cr — a cost overrun of -0.3%. Expenditure to date: ₹238 Cr (9.2% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Vadodara Mumbai Expressway Karvad - Jujuwa from Km. 128.000 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618467. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Vadodara Mumbai Expressway Karvad - Jujuwa from Km. 128.000 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.