Vadodara Mumbai Expressway Ena -Kim Phase IB - Pkg VI [Km 217.500 to Km 254.430]
Original Cost
₹2272 Cr
Baseline estimate
Revised Cost
₹4297 Cr
Latest approved cost
Expenditure
₹2574 Cr
Spent to date
Utilization
59.9%
Of revised budget
Cost Status
+89.1%
+₹2025 Cr increase
Remaining
₹1723 Cr
Budget left
Budget Utilization
59.9%Spent
₹2574 Cr
Remaining
₹1723 Cr
Total
₹4297 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2272 Cr
Revised Cost
₹4297 Cr
Increase
+₹2025 Cr
Escalation
+89.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
10/12/2023
Revised Completion
15/05/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹2025 Cr (89.1%) from the original estimate of ₹2272 Cr.
Expenditure stands at ₹2574 Cr, which is 59.9% of the revised project cost.
Remaining budget: ₹1723 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Vadodara Mumbai Expressway Ena -Kim Phase IB - Pkg VI [Km 217.500 to Km 254.430] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2272.00 Cr, later revised to ₹4297.28 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Vadodara Mumbai Expressway Ena -Kim Phase IB - Pkg VI [Km 217.500 to Km 254.430]"?
- Vadodara Mumbai Expressway Ena -Kim Phase IB - Pkg VI [Km 217.500 to Km 254.430] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹2272 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2272 Cr and has been revised to ₹4297 Cr — a cost overrun of +89.1%. Expenditure to date: ₹2574 Cr (59.9% of revised cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- Vadodara Mumbai Expressway Ena -Kim Phase IB - Pkg VI [Km 21 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618464. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Vadodara Mumbai Expressway Ena -Kim Phase IB - Pkg VI [Km 21 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.