Original Cost
₹2272 Cr
Baseline estimate
Revised Cost
₹4297 Cr
Latest approved cost
Expenditure
₹2574 Cr
Spent to date
Utilization
59.9%
Of revised budget
Cost Status
+89.1%
+₹2025 Cr increase
Remaining
₹1723 Cr
Budget left
Spent
₹2574 Cr
Remaining
₹1723 Cr
Total
₹4297 Cr
Original Cost
₹2272 Cr
Revised Cost
₹4297 Cr
Increase
+₹2025 Cr
Escalation
+89.1%
Project Approved
Construction / Implementation
Original End Date
10/12/2023
Revised Completion
15/05/2026
Completed
Cost has increased by ₹2025 Cr (89.1%) from the original estimate of ₹2272 Cr.
Expenditure stands at ₹2574 Cr, which is 59.9% of the revised project cost.
Remaining budget: ₹1723 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.