Original Cost
₹1253 Cr
Baseline estimate
Revised Cost
₹1371 Cr
Latest approved cost
Expenditure
₹482 Cr
Spent to date
Utilization
35.2%
Of revised budget
Cost Status
+9.4%
+₹118 Cr increase
Remaining
₹889 Cr
Budget left
Spent
₹482 Cr
Remaining
₹889 Cr
Total
₹1371 Cr
Original Cost
₹1253 Cr
Revised Cost
₹1371 Cr
Increase
+₹118 Cr
Escalation
+9.4%
Project Approved
Construction / Implementation
Original End Date
18/07/2021
Revised Completion
30/06/2026
Completed
Cost has increased by ₹118 Cr (9.4%) from the original estimate of ₹1253 Cr.
Expenditure stands at ₹482 Cr, which is 35.2% of the revised project cost.
Remaining budget: ₹889 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.