Original Cost
₹581 Cr
Baseline estimate
Revised Cost
₹896 Cr
Latest approved cost
Expenditure
₹713 Cr
Spent to date
Utilization
79.6%
Of revised budget
Cost Status
+54.2%
+₹315 Cr increase
Remaining
₹182 Cr
Budget left
Spent
₹713 Cr
Remaining
₹182 Cr
Total
₹896 Cr
Original Cost
₹581 Cr
Revised Cost
₹896 Cr
Increase
+₹315 Cr
Escalation
+54.2%
Project Approved
Construction / Implementation
Original End Date
30/06/2022
Revised Completion
31/12/2026
Completed
Cost has increased by ₹315 Cr (54.2%) from the original estimate of ₹581 Cr.
Expenditure stands at ₹713 Cr, which is 79.6% of the revised project cost.
Remaining budget: ₹182 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.