Original Cost
₹770 Cr
Baseline estimate
Revised Cost
₹1606 Cr
Latest approved cost
Expenditure
₹1516 Cr
Spent to date
Utilization
94.4%
Of revised budget
Cost Status
+108.6%
+₹836 Cr increase
Remaining
₹90 Cr
Budget left
Spent
₹1516 Cr
Remaining
₹90 Cr
Total
₹1606 Cr
Original Cost
₹770 Cr
Revised Cost
₹1606 Cr
Increase
+₹836 Cr
Escalation
+108.6%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/03/2026
Completed
Cost has increased by ₹836 Cr (108.6%) from the original estimate of ₹770 Cr.
Expenditure stands at ₹1516 Cr, which is 94.4% of the revised project cost.
Remaining budget: ₹90 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.