Upgradation of two lane paved shoulder from Shahpura existing km. 0.00 Design Ch. 000 to Thanagazi existing Km.37352 Design Ch. 36810 of NH-248A on EPC mode in the State of Rajasthan.
Original Cost
₹174 Cr
Baseline estimate
Revised Cost
₹174 Cr
Latest approved cost
Expenditure
₹64 Cr
Spent to date
Utilization
36.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹110 Cr
Budget left
Budget Utilization
36.5%Spent
₹64 Cr
Remaining
₹110 Cr
Total
₹174 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/07/2024
Revised Completion
31/07/2025
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹174 Cr — no cost escalation recorded.
Expenditure stands at ₹64 Cr, which is 36.5% of the revised project cost.
Remaining budget: ₹110 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Upgradation of two lane paved shoulder from Shahpura existing km. 0.00 Design Ch. 000 to Thanagazi existing Km.37352 Design Ch. 36810 of NH-248A on EPC mode in the State of Rajasthan. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹174.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Upgradation of two lane paved shoulder from Shahpura existing km. 0.00 Design "?
- Upgradation of two lane paved shoulder from Shahpura existing km. 0.00 Design Ch. 000 to Thanagazi existing Km.37352 Design Ch. 36810 of NH-248A on EPC mode in the State of Rajasthan. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Rajasthan. Original cost: ₹174 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹174 Cr has not been significantly revised. Expenditure: ₹64 Cr (36.5% of cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- Upgradation of two lane paved shoulder from Shahpura existin is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618118. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Upgradation of two lane paved shoulder from Shahpura existin is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.