Upgradation of Keonchi - Ratanpur Road of NH 45 Package-II, from design chainage km 278.75 to km 321.348 of length 42.598 km to two lane with paved shoulders under Corridor scheme on EPC mode in the state of Chhattisgarh.
Original Cost
₹286 Cr
Baseline estimate
Revised Cost
₹286 Cr
Latest approved cost
Expenditure
₹126 Cr
Spent to date
Utilization
43.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹160 Cr
Budget left
Budget Utilization
43.9%Spent
₹126 Cr
Remaining
₹160 Cr
Total
₹286 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
06/01/2026
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹286 Cr — no cost escalation recorded.
Expenditure stands at ₹126 Cr, which is 43.9% of the revised project cost.
Remaining budget: ₹160 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Upgradation of Keonchi - Ratanpur Road of NH 45 Package-II, from design chainage km 278.75 to km 321.348 of length 42.598 km to two lane with paved shoulders under Corridor scheme on EPC mode in the state of Chhattisgarh. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹286.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Upgradation of Keonchi - Ratanpur Road of NH 45 Package-II, from design chainage"?
- Upgradation of Keonchi - Ratanpur Road of NH 45 Package-II, from design chainage km 278.75 to km 321.348 of length 42.598 km to two lane with paved shoulders under Corridor scheme on EPC mode in the state of Chhattisgarh. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Chhattisgarh. Original cost: ₹286 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹286 Cr has not been significantly revised. Expenditure: ₹126 Cr (43.9% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Upgradation of Keonchi - Ratanpur Road of NH 45 Package-II, is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618017. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Upgradation of Keonchi - Ratanpur Road of NH 45 Package-II, is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.