Original Cost
₹225 Cr
Baseline estimate
Revised Cost
₹229 Cr
Latest approved cost
Expenditure
₹71 Cr
Spent to date
Utilization
31.0%
Of revised budget
Cost Status
+1.7%
+₹4 Cr increase
Remaining
₹158 Cr
Budget left
Spent
₹71 Cr
Remaining
₹158 Cr
Total
₹229 Cr
Original Cost
₹225 Cr
Revised Cost
₹229 Cr
Increase
+₹4 Cr
Escalation
+1.7%
Project Approved
Construction / Implementation
Original End Date
06/01/2026
Revised Completion
31/12/2026
Completed
Cost has increased by ₹4 Cr (1.7%) from the original estimate of ₹225 Cr.
Expenditure stands at ₹71 Cr, which is 31.0% of the revised project cost.
Remaining budget: ₹158 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.