Roads & HighwaysIPM · Central Project +1.7% overrun#618015

Upgradation of Keonchi - Ratanpur Road of NH 45 Package-I, from design chainage km 237.860 to km 273.200 of length 35.340 km to two lane with paved shoulders under Corridor scheme on EPC mode in the state of Chhattisgarh.

Ministry of Road Transport & HighwaysChhattisgarh
Revised Cost: ₹229 CrUtilization: 43.3%Overrun: +₹4 Cr

Original Cost

₹225 Cr

Baseline estimate

+2% overrun

Revised Cost

₹229 Cr

Latest approved cost

Expenditure

₹99 Cr

Spent to date

Utilization

43.3%

Of revised budget

Escalated

Cost Status

+1.7%

+₹4 Cr increase

Remaining

₹130 Cr

Budget left

Budget Utilization

43.3%
0%25%50%75%100%

Spent

₹99 Cr

Remaining

₹130 Cr

Total

₹229 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹225 Cr

Revised Cost

₹229 Cr

Increase

+₹4 Cr

Escalation

+1.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/01/2026

Revised Completion

31/12/2026

Completed

Project Details

Project Code618015
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateChhattisgarh
Data Month2026-08

Financial Summary

Original Cost₹225 Cr
Revised Cost₹229 Cr
Expenditure₹99 Cr
Original End Date06/01/2026
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹4 Cr (1.7%) from the original estimate of ₹225 Cr.

Expenditure stands at ₹99 Cr, which is 43.3% of the revised project cost.

Remaining budget: ₹130 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Upgradation of Keonchi - Ratanpur Road of NH 45 Package-I, from design chainage km 237.860 to km 273.200 of length 35.340 km to two lane with paved shoulders under Corridor scheme on EPC mode in the state of Chhattisgarh. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹225.00 Cr, later revised to ₹228.93 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Upgradation of Keonchi - Ratanpur Road of NH 45 Package-I, from design chainage "?
Upgradation of Keonchi - Ratanpur Road of NH 45 Package-I, from design chainage km 237.860 to km 273.200 of length 35.340 km to two lane with paved shoulders under Corridor scheme on EPC mode in the state of Chhattisgarh. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Chhattisgarh. Original cost: ₹225 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹225 Cr and has been revised to ₹229 Cr — a cost overrun of +1.7%. Expenditure to date: ₹99 Cr (43.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Upgradation of Keonchi - Ratanpur Road of NH 45 Package-I, f is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618015. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Upgradation of Keonchi - Ratanpur Road of NH 45 Package-I, f is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.