Roads & HighwaysIPM · Central Project#618158

Upgradation of Goras to Shyampur Road section of NH-552 Ext., from Design Chainge 48.400 to 111.800 Km Total length 63.40 km to two lane with paved shoulder configuration along with One time improvement of 8.91 km in the state of Madhya Pradesh on EPC mode

Ministry of Road Transport & HighwaysMadhya Pradesh
Revised Cost: ₹417 CrUtilization: 13.6%

Original Cost

₹417 Cr

Baseline estimate

On budget

Revised Cost

₹417 Cr

Latest approved cost

Expenditure

₹57 Cr

Spent to date

Utilization

13.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹360 Cr

Budget left

Budget Utilization

13.6%
0%25%50%75%100%

Spent

₹57 Cr

Remaining

₹360 Cr

Total

₹417 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/12/2026

Revised Completion

30/12/2026

Completed

Project Details

Project Code618158
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMadhya Pradesh
Data Month2026-08

Financial Summary

Original Cost₹417 Cr
Revised Cost₹417 Cr
Expenditure₹57 Cr
Original End Date30/12/2026
Revised Date30/12/2026

Project Intelligence

Project is within original budget of ₹417 Cr — no cost escalation recorded.

Expenditure stands at ₹57 Cr, which is 13.6% of the revised project cost.

Remaining budget: ₹360 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Upgradation of Goras to Shyampur Road section of NH-552 Ext., from Design Chainge 48.400 to 111.800 Km Total length 63.40 km to two lane with paved shoulder configuration along with One time improvement of 8.91 km in the state of Madhya Pradesh on EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹417.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Upgradation of Goras to Shyampur Road section of NH-552 Ext., from Design Chaing"?
Upgradation of Goras to Shyampur Road section of NH-552 Ext., from Design Chainge 48.400 to 111.800 Km Total length 63.40 km to two lane with paved shoulder configuration along with One time improvement of 8.91 km in the state of Madhya Pradesh on EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹417 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹417 Cr has not been significantly revised. Expenditure: ₹57 Cr (13.6% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Upgradation of Goras to Shyampur Road section of NH-552 Ext. is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618158. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Upgradation of Goras to Shyampur Road section of NH-552 Ext. is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.