Oil & GasIPM · Central Project#701350

Upgradation of Facilities of Numaligarh-Siliguri Product Pipeline [NSPL] for transportation of additional products from existing 1.72 MMTPA to 5.5 MMTPA

Ministry of Petroleum & Natural GasAssam
Revised Cost: ₹860 CrUtilization: 74.1%

Original Cost

₹860 Cr

Baseline estimate

On budget

Revised Cost

₹860 Cr

Latest approved cost

Expenditure

₹637 Cr

Spent to date

Utilization

74.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹223 Cr

Budget left

Budget Utilization

74.1%
0%25%50%75%100%

Spent

₹637 Cr

Remaining

₹223 Cr

Total

₹860 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/12/2024

Revised Completion

31/03/2026

Completed

Project Details

Project Code701350
SectorOil & Gas
MinistryMinistry of Petroleum & Natural Gas
StateAssam
Data Month2026-02

Financial Summary

Original Cost₹860 Cr
Revised Cost₹860 Cr
Expenditure₹637 Cr
Original End Date20/12/2024
Revised Date31/03/2026

Project Intelligence

Project is within original budget of ₹860 Cr — no cost escalation recorded.

Expenditure stands at ₹637 Cr, which is 74.1% of the revised project cost.

Remaining budget: ₹223 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.

Upgradation of Facilities of Numaligarh-Siliguri Product Pipeline [NSPL] for transportation of additional products from existing 1.72 MMTPA to 5.5 MMTPA is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹860.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Upgradation of Facilities of Numaligarh-Siliguri Product Pipeline [NSPL] for tra"?
Upgradation of Facilities of Numaligarh-Siliguri Product Pipeline [NSPL] for transportation of additional products from existing 1.72 MMTPA to 5.5 MMTPA is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Assam. Original cost: ₹860 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹860 Cr has not been significantly revised. Expenditure: ₹637 Cr (74.1% of cost). Data as of 2026-02.
QWhich ministry is responsible for this project?
Upgradation of Facilities of Numaligarh-Siliguri Product Pip is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 701350. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Upgradation of Facilities of Numaligarh-Siliguri Product Pip is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.