Oil & GasIPM · Central Project +28.0% overrun#400168

500 KTA PDHPP Project, Usar

Ministry of Petroleum & Natural GasMaharashtra
Revised Cost: ₹11.3K CrUtilization: 79.7%Overrun: +₹2459 Cr

Original Cost

₹8797 Cr

Baseline estimate

+28% overrun

Revised Cost

₹11.3K Cr

Latest approved cost

Expenditure

₹8972 Cr

Spent to date

Utilization

79.7%

Of revised budget

Escalated

Cost Status

+28.0%

+₹2459 Cr increase

Remaining

₹2284 Cr

Budget left

Budget Utilization

79.7%
0%25%50%75%100%

Spent

₹8972 Cr

Remaining

₹2284 Cr

Total

₹11.3K Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹8797 Cr

Revised Cost

₹11.3K Cr

Increase

+₹2459 Cr

Escalation

+28.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

08/04/2025

Revised Completion

30/06/2027

Completed

Project Details

Project Code400168
SectorOil & Gas
MinistryMinistry of Petroleum & Natural Gas
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹8797 Cr
Revised Cost₹11.3K Cr
Expenditure₹8972 Cr
Original End Date08/04/2025
Revised Date30/06/2027

Project Intelligence

Mega infrastructure project worth ₹11.3K Cr — among the largest central projects in Maharashtra.

Cost has increased by ₹2459 Cr (28.0%) from the original estimate of ₹8797 Cr.

Expenditure stands at ₹8972 Cr, which is 79.7% of the revised project cost.

Remaining budget: ₹2284 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.

500 KTA PDHPP Project, Usar is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹8797.00 Cr, later revised to ₹11256.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "500 KTA PDHPP Project, Usar"?
500 KTA PDHPP Project, Usar is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Maharashtra. Original cost: ₹8797 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹8797 Cr and has been revised to ₹11256 Cr — a cost overrun of +28%. Expenditure to date: ₹8972 Cr (79.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
500 KTA PDHPP Project, Usar is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 400168. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 500 KTA PDHPP Project, Usar is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.