Upgradation of Existing Two Lane Carriageway to Two Lane Carriageway with Paved Shoulder from Ch. 665686 Existing Km. 665.686 in Khanpur Village in Vansda Taluka to Ch. 710470 Existing Km. 710.483 in Karvad Village in Vapi Taluka Length 44.784 Km Section of NH-56 in the State of Gujarat on EPC Mode

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹647 CrUtilization: 1.4%

Original Cost

₹647 Cr

Baseline estimate

On budget

Revised Cost

₹647 Cr

Latest approved cost

Expenditure

₹9 Cr

Spent to date

Utilization

1.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹638 Cr

Budget left

Budget Utilization

1.4%
0%25%50%75%100%

Spent

₹9 Cr

Remaining

₹638 Cr

Total

₹647 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/07/2028

Revised Completion

20/07/2028

Completed

Project Details

Project Code619297
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹647 Cr
Revised Cost₹647 Cr
Expenditure₹9 Cr
Original End Date20/07/2028
Revised Date20/07/2028

Project Intelligence

Project is within original budget of ₹647 Cr — no cost escalation recorded.

Expenditure stands at ₹9 Cr, which is 1.4% of the revised project cost.

Remaining budget: ₹638 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Upgradation of Existing Two Lane Carriageway to Two Lane Carriageway with Paved Shoulder from Ch. 665686 Existing Km. 665.686 in Khanpur Village in Vansda Taluka to Ch. 710470 Existing Km. 710.483 in Karvad Village in Vapi Taluka Length 44.784 Km Section of NH-56 in the State of Gujarat on EPC Mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹647.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Upgradation of Existing Two Lane Carriageway to Two Lane Carriageway with Paved "?
Upgradation of Existing Two Lane Carriageway to Two Lane Carriageway with Paved Shoulder from Ch. 665686 Existing Km. 665.686 in Khanpur Village in Vansda Taluka to Ch. 710470 Existing Km. 710.483 in Karvad Village in Vapi Taluka Length 44.784 Km Section of NH-56 in the State of Gujarat on EPC Mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹647 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹647 Cr has not been significantly revised. Expenditure: ₹9 Cr (1.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Upgradation of Existing Two Lane Carriageway to Two Lane Car is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619297. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Upgradation of Existing Two Lane Carriageway to Two Lane Car is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.