Upgradation and reconstruction of Shahpura-Dindori Section of NH 45 from Km 103.700 Design to Km 164.580 Design including 3 bypasses Total length 60.88km to Two lane with paved shoulder configuration along with One time improvement in 03 nos of bypassed built-up areas in a total length of 12.341 km in the State of Madhya Pradesh on EPC mode
Original Cost
₹241 Cr
Baseline estimate
Revised Cost
₹250 Cr
Latest approved cost
Expenditure
₹130 Cr
Spent to date
Utilization
51.9%
Of revised budget
Cost Status
+3.8%
+₹9 Cr increase
Remaining
₹120 Cr
Budget left
Budget Utilization
51.9%Spent
₹130 Cr
Remaining
₹120 Cr
Total
₹250 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹241 Cr
Revised Cost
₹250 Cr
Increase
+₹9 Cr
Escalation
+3.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
11/12/2025
Revised Completion
30/06/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹9 Cr (3.8%) from the original estimate of ₹241 Cr.
Expenditure stands at ₹130 Cr, which is 51.9% of the revised project cost.
Remaining budget: ₹120 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Upgradation and reconstruction of Shahpura-Dindori Section of NH 45 from Km 103.700 Design to Km 164.580 Design including 3 bypasses Total length 60.88km to Two lane with paved shoulder configuration along with One time improvement in 03 nos of bypassed built-up areas in a total length of 12.341 km in the State of Madhya Pradesh on EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹241.00 Cr, later revised to ₹250.09 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Upgradation and reconstruction of Shahpura-Dindori Section of NH 45 from Km 103."?
- Upgradation and reconstruction of Shahpura-Dindori Section of NH 45 from Km 103.700 Design to Km 164.580 Design including 3 bypasses Total length 60.88km to Two lane with paved shoulder configuration along with One time improvement in 03 nos of bypassed built-up areas in a total length of 12.341 km in the State of Madhya Pradesh on EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹241 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹241 Cr and has been revised to ₹250 Cr — a cost overrun of +3.8%. Expenditure to date: ₹130 Cr (51.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Upgradation and reconstruction of Shahpura-Dindori Section o is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617914. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Upgradation and reconstruction of Shahpura-Dindori Section o is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.