Original Cost
₹492 Cr
Baseline estimate
Revised Cost
₹524 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
+6.4%
+₹32 Cr increase
Remaining
₹524 Cr
Budget left
Spent
₹0 Cr
Remaining
₹524 Cr
Total
₹524 Cr
Original Cost
₹492 Cr
Revised Cost
₹524 Cr
Increase
+₹32 Cr
Escalation
+6.4%
Project Approved
Construction / Implementation
Original End Date
28/07/2026
Revised Completion
28/07/2026
Completed
Cost has increased by ₹32 Cr (6.4%) from the original estimate of ₹492 Cr.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹524 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.