Roads & HighwaysIPM · Central Project#619155

Upgradation and 4L of Haridwar Bypass from Km 0.000 Km 188.100 of NH-58 to Km. 15.100 Km 5.100 of NH 74 PKg-1

Ministry of Road Transport & HighwaysUttarakhand
Revised Cost: ₹1424 CrUtilization: 54.1%

Original Cost

₹1603 Cr

Baseline estimate

On budget

Revised Cost

₹1424 Cr

Latest approved cost

Expenditure

₹770 Cr

Spent to date

Utilization

54.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹654 Cr

Budget left

Budget Utilization

54.1%
0%25%50%75%100%

Spent

₹770 Cr

Remaining

₹654 Cr

Total

₹1424 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

29/10/2024

Revised Completion

30/11/2026

Completed

Project Details

Project Code619155
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttarakhand
Data Month2026-08

Financial Summary

Original Cost₹1603 Cr
Revised Cost₹1424 Cr
Expenditure₹770 Cr
Original End Date29/10/2024
Revised Date30/11/2026

Project Intelligence

Project is within original budget of ₹1603 Cr — no cost escalation recorded.

Expenditure stands at ₹770 Cr, which is 54.1% of the revised project cost.

Remaining budget: ₹654 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Upgradation and 4L of Haridwar Bypass from Km 0.000 Km 188.100 of NH-58 to Km. 15.100 Km 5.100 of NH 74 PKg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1603.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Upgradation and 4L of Haridwar Bypass from Km 0.000 Km 188.100 of NH-58 to Km. 1"?
Upgradation and 4L of Haridwar Bypass from Km 0.000 Km 188.100 of NH-58 to Km. 15.100 Km 5.100 of NH 74 PKg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹1603 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1603 Cr and has been revised to ₹1424 Cr — a cost overrun of -11.2%. Expenditure to date: ₹770 Cr (54.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Upgradation and 4L of Haridwar Bypass from Km 0.000 Km 188.1 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619155. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Upgradation and 4L of Haridwar Bypass from Km 0.000 Km 188.1 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.