Up-gradation to 2/4 lane with paved shoulder configuration of NH-652 from Tuljapur Naldurg-Akkalkot road Chainage from Km. 00.000 to km 30.982 in the State of Maharashtra on EPC mode.
Original Cost
₹183 Cr
Baseline estimate
Revised Cost
₹183 Cr
Latest approved cost
Expenditure
₹86 Cr
Spent to date
Utilization
46.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹97 Cr
Budget left
Budget Utilization
46.8%Spent
₹86 Cr
Remaining
₹97 Cr
Total
₹183 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
08/07/2026
Revised Completion
10/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹183 Cr — no cost escalation recorded.
Expenditure stands at ₹86 Cr, which is 46.8% of the revised project cost.
Remaining budget: ₹97 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Up-gradation to 2/4 lane with paved shoulder configuration of NH-652 from Tuljapur Naldurg-Akkalkot road Chainage from Km. 00.000 to km 30.982 in the State of Maharashtra on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹183.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Up-gradation to 2/4 lane with paved shoulder configuration of NH-652 from Tuljap"?
- Up-gradation to 2/4 lane with paved shoulder configuration of NH-652 from Tuljapur Naldurg-Akkalkot road Chainage from Km. 00.000 to km 30.982 in the State of Maharashtra on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹183 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹183 Cr has not been significantly revised. Expenditure: ₹86 Cr (46.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Up-gradation to 2/4 lane with paved shoulder configuration o is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618049. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Up-gradation to 2/4 lane with paved shoulder configuration o is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.