Roads & HighwaysIPM · Central Project#618394

Up-gradation to 2-lane with Paved Shoulder from Km 12.850 to Km20.300 of 7.450Km length on Goha-Khellani section and a link road to Goha village of 2.016 km on NH-244 in UT of Jammu and Kashmir on EPC Mode Pkg-1

Ministry of Road Transport & HighwaysJammu & Kashmir
Revised Cost: ₹225 CrUtilization: 81.3%

Original Cost

₹228 Cr

Baseline estimate

On budget

Revised Cost

₹225 Cr

Latest approved cost

Expenditure

₹183 Cr

Spent to date

Utilization

81.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹42 Cr

Budget left

Budget Utilization

81.3%
0%25%50%75%100%

Spent

₹183 Cr

Remaining

₹42 Cr

Total

₹225 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

01/04/2022

Revised Completion

31/10/2026

Completed

Project Details

Project Code618394
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJammu & Kashmir
Data Month2026-08

Financial Summary

Original Cost₹228 Cr
Revised Cost₹225 Cr
Expenditure₹183 Cr
Original End Date01/04/2022
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹228 Cr — no cost escalation recorded.

Expenditure stands at ₹183 Cr, which is 81.3% of the revised project cost.

Remaining budget: ₹42 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Up-gradation to 2-lane with Paved Shoulder from Km 12.850 to Km20.300 of 7.450Km length on Goha-Khellani section and a link road to Goha village of 2.016 km on NH-244 in UT of Jammu and Kashmir on EPC Mode Pkg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹228.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Up-gradation to 2-lane with Paved Shoulder from Km 12.850 to Km20.300 of 7.450Km"?
Up-gradation to 2-lane with Paved Shoulder from Km 12.850 to Km20.300 of 7.450Km length on Goha-Khellani section and a link road to Goha village of 2.016 km on NH-244 in UT of Jammu and Kashmir on EPC Mode Pkg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹228 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹228 Cr and has been revised to ₹225 Cr — a cost overrun of -1.2%. Expenditure to date: ₹183 Cr (81.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Up-gradation to 2-lane with Paved Shoulder from Km 12.850 to is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618394. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Up-gradation to 2-lane with Paved Shoulder from Km 12.850 to is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.