Roads & HighwaysIPM · Central Project +17.9% overrun#617906

Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-927D from Design Chainage km 0/00 to km 58/115 to Two lane with PS configuration in the State of Gujarat on EPC

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹291 CrUtilization: 0.0%Overrun: +₹44 Cr

Original Cost

₹247 Cr

Baseline estimate

+18% overrun

Revised Cost

₹291 Cr

Latest approved cost

Expenditure

₹0 Cr

Spent to date

Utilization

0.0%

Of revised budget

Escalated

Cost Status

+17.9%

+₹44 Cr increase

Remaining

₹291 Cr

Budget left

Budget Utilization

0.0%
0%25%50%75%100%

Spent

₹0 Cr

Remaining

₹291 Cr

Total

₹291 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹247 Cr

Revised Cost

₹291 Cr

Increase

+₹44 Cr

Escalation

+17.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

24/01/2027

Revised Completion

24/01/2027

Completed

Project Details

Project Code617906
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹247 Cr
Revised Cost₹291 Cr
Expenditure₹0 Cr
Original End Date24/01/2027
Revised Date24/01/2027

Project Intelligence

Cost has increased by ₹44 Cr (17.9%) from the original estimate of ₹247 Cr.

Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.

Remaining budget: ₹291 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-927D from Design Chainage km 0/00 to km 58/115 to Two lane with PS configuration in the State of Gujarat on EPC is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹247.00 Cr, later revised to ₹291.19 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-927D from Design Chain"?
Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-927D from Design Chainage km 0/00 to km 58/115 to Two lane with PS configuration in the State of Gujarat on EPC is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹247 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹247 Cr and has been revised to ₹291 Cr — a cost overrun of +17.9%. Expenditure to date: ₹0 Cr (N/A% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-92 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617906. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-92 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.