Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-927D from Design Chainage km 0/00 to km 58/115 to Two lane with PS configuration in the State of Gujarat on EPC
Original Cost
₹247 Cr
Baseline estimate
Revised Cost
₹291 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
+17.9%
+₹44 Cr increase
Remaining
₹291 Cr
Budget left
Budget Utilization
0.0%Spent
₹0 Cr
Remaining
₹291 Cr
Total
₹291 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹247 Cr
Revised Cost
₹291 Cr
Increase
+₹44 Cr
Escalation
+17.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
24/01/2027
Revised Completion
24/01/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹44 Cr (17.9%) from the original estimate of ₹247 Cr.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹291 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-927D from Design Chainage km 0/00 to km 58/115 to Two lane with PS configuration in the State of Gujarat on EPC is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹247.00 Cr, later revised to ₹291.19 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-927D from Design Chain"?
- Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-927D from Design Chainage km 0/00 to km 58/115 to Two lane with PS configuration in the State of Gujarat on EPC is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹247 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹247 Cr and has been revised to ₹291 Cr — a cost overrun of +17.9%. Expenditure to date: ₹0 Cr (N/A% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-92 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617906. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-92 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.