approach Road - Bheja-Bakaur
Original Cost
₹1200 Cr
Baseline estimate
Revised Cost
₹1224 Cr
Latest approved cost
Expenditure
₹1121 Cr
Spent to date
Utilization
91.6%
Of revised cost
Cost Overrun
+2.0%
+₹24 Cr
Remaining
₹103 Cr
Budget left
Spent
₹1121 Cr
Remaining
₹103 Cr
Total
₹1224 Cr
91.6%
Utilized
Original Cost
₹1200 Cr
Revised Cost
₹1224 Cr
Increase
+₹24 Cr
Escalation
+2.0%
Project Approved
Construction / Implementation
Original End Date
2023-08-11
Revised Completion
2027-03-31
Completed
Cost has increased by ₹24 Cr (2.0%) from the original estimate of ₹1200 Cr.
Expenditure stands at ₹1121 Cr, which is 91.6% of the revised project cost.
Remaining budget: ₹103 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.