Original Cost
₹297 Cr
Baseline estimate
Revised Cost
₹289 Cr
Latest approved cost
Expenditure
₹238 Cr
Spent to date
Utilization
82.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹52 Cr
Budget left
Spent
₹238 Cr
Remaining
₹52 Cr
Total
₹289 Cr
Project Approved
Construction / Implementation
Original End Date
07/09/2023
Revised Completion
09/04/2024
Completed
Project is within original budget of ₹297 Cr — no cost escalation recorded.
Expenditure stands at ₹238 Cr, which is 82.2% of the revised project cost.
Remaining budget: ₹52 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.