RailwaysIPM · Central Project#705496

Tumkur-Chitradurg-Davangere 199.7 km

Ministry of RailwaysKarnataka
Revised Cost: ₹1801 CrUtilization: 37.6%

Original Cost

₹1876 Cr

Baseline estimate

On budget

Revised Cost

₹1801 Cr

Latest approved cost

Expenditure

₹677 Cr

Spent to date

Utilization

37.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1124 Cr

Budget left

Budget Utilization

37.6%
0%25%50%75%100%

Spent

₹677 Cr

Remaining

₹1124 Cr

Total

₹1801 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2019

Revised Completion

31/12/2027

Completed

Project Details

Project Code705496
SectorRailways
MinistryMinistry of Railways
StateKarnataka
Data Month2026-07

Financial Summary

Original Cost₹1876 Cr
Revised Cost₹1801 Cr
Expenditure₹677 Cr
Original End Date31/03/2019
Revised Date31/12/2027

Project Intelligence

Project is within original budget of ₹1876 Cr — no cost escalation recorded.

Expenditure stands at ₹677 Cr, which is 37.6% of the revised project cost.

Remaining budget: ₹1124 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Tumkur-Chitradurg-Davangere 199.7 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1876.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Tumkur-Chitradurg-Davangere 199.7 km"?
Tumkur-Chitradurg-Davangere 199.7 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Karnataka. Original cost: ₹1876 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1876 Cr and has been revised to ₹1801 Cr — a cost overrun of -4%. Expenditure to date: ₹677 Cr (37.6% of revised cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
Tumkur-Chitradurg-Davangere 199.7 km is under the Ministry of Railways in the Railways sector. Project code: 705496. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Tumkur-Chitradurg-Davangere 199.7 km is one of several Bihar projects tracked under the Railways sector on the IPM system.