Tumkur-Chitradurg-Davangere 199.7 km
Original Cost
₹1876 Cr
Baseline estimate
Revised Cost
₹1801 Cr
Latest approved cost
Expenditure
₹677 Cr
Spent to date
Utilization
37.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1124 Cr
Budget left
Budget Utilization
37.6%Spent
₹677 Cr
Remaining
₹1124 Cr
Total
₹1801 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2019
Revised Completion
31/12/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1876 Cr — no cost escalation recorded.
Expenditure stands at ₹677 Cr, which is 37.6% of the revised project cost.
Remaining budget: ₹1124 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Tumkur-Chitradurg-Davangere 199.7 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1876.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Tumkur-Chitradurg-Davangere 199.7 km"?
- Tumkur-Chitradurg-Davangere 199.7 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Karnataka. Original cost: ₹1876 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1876 Cr and has been revised to ₹1801 Cr — a cost overrun of -4%. Expenditure to date: ₹677 Cr (37.6% of revised cost). Data as of 2026-07.
- QWhich ministry is responsible for this project?
- Tumkur-Chitradurg-Davangere 199.7 km is under the Ministry of Railways in the Railways sector. Project code: 705496. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Tumkur-Chitradurg-Davangere 199.7 km is one of several Bihar projects tracked under the Railways sector on the IPM system.