Treatment of landslide zone from location no. 01 to 28 km 62.860 to 152.750 on NH-12509 in the State of Uttarakhand under EPC mode in NHO Annual Plan 2022-23
Original Cost
₹192 Cr
Baseline estimate
Revised Cost
₹192 Cr
Latest approved cost
Expenditure
₹139 Cr
Spent to date
Utilization
72.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹53 Cr
Budget left
Budget Utilization
72.5%Spent
₹139 Cr
Remaining
₹53 Cr
Total
₹192 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
20/06/2024
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹192 Cr — no cost escalation recorded.
Expenditure stands at ₹139 Cr, which is 72.5% of the revised project cost.
Remaining budget: ₹53 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Treatment of landslide zone from location no. 01 to 28 km 62.860 to 152.750 on NH-12509 in the State of Uttarakhand under EPC mode in NHO Annual Plan 2022-23 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹192.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Treatment of landslide zone from location no. 01 to 28 km 62.860 to 152.750 on N"?
- Treatment of landslide zone from location no. 01 to 28 km 62.860 to 152.750 on NH-12509 in the State of Uttarakhand under EPC mode in NHO Annual Plan 2022-23 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹192 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹192 Cr has not been significantly revised. Expenditure: ₹139 Cr (72.5% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Treatment of landslide zone from location no. 01 to 28 km 62 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617889. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Treatment of landslide zone from location no. 01 to 28 km 62 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.