Original Cost
₹6339 Cr
Baseline estimate
Revised Cost
₹6339 Cr
Latest approved cost
Expenditure
₹4201 Cr
Spent to date
Utilization
66.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2138 Cr
Budget left
Spent
₹4201 Cr
Remaining
₹2138 Cr
Total
₹6339 Cr
Project Approved
Construction / Implementation
Original End Date
01/03/2025
Revised Completion
31/01/2028
Completed
Project is within original budget of ₹6339 Cr — no cost escalation recorded.
Expenditure stands at ₹4201 Cr, which is 66.3% of the revised project cost.
Remaining budget: ₹2138 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.