RailwaysIPM · Central Project#400234

Third Railway Line between Patratu-Sonnagar [291 kms]

Ministry of RailwaysJharkhand
Revised Cost: ₹8975 CrUtilization: 53.5%

Original Cost

₹8975 Cr

Baseline estimate

On budget

Revised Cost

₹8975 Cr

Latest approved cost

Expenditure

₹4799 Cr

Spent to date

Utilization

53.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹4176 Cr

Budget left

Budget Utilization

53.5%
0%25%50%75%100%

Spent

₹4799 Cr

Remaining

₹4176 Cr

Total

₹8975 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2026

Revised Completion

31/12/2028

Completed

Project Details

Project Code400234
SectorRailways
MinistryMinistry of Railways
StateJharkhand
Data Month2025-12

Financial Summary

Original Cost₹8975 Cr
Revised Cost₹8975 Cr
Expenditure₹4799 Cr
Original End Date31/03/2026
Revised Date31/12/2028

Project Intelligence

Project is within original budget of ₹8975 Cr — no cost escalation recorded.

Expenditure stands at ₹4799 Cr, which is 53.5% of the revised project cost.

Remaining budget: ₹4176 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Third Railway Line between Patratu-Sonnagar [291 kms] is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹8975.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Third Railway Line between Patratu-Sonnagar [291 kms]"?
Third Railway Line between Patratu-Sonnagar [291 kms] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Jharkhand. Original cost: ₹8975 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹8975 Cr has not been significantly revised. Expenditure: ₹4799 Cr (53.5% of cost). Data as of 2025-12.
QWhich ministry is responsible for this project?
Third Railway Line between Patratu-Sonnagar [291 kms] is under the Ministry of Railways in the Railways sector. Project code: 400234. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Third Railway Line between Patratu-Sonnagar [291 kms] is one of several Bihar projects tracked under the Railways sector on the IPM system.