Patratu-Sonnagar [291 kms]
Original Cost
₹8975 Cr
Baseline estimate
Revised Cost
₹8975 Cr
Latest approved cost
Expenditure
₹4799 Cr
Spent to date
Utilization
53.5%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹4176 Cr
Budget left
Spent
₹4799 Cr
Remaining
₹4176 Cr
Total
₹8975 Cr
53.5%
Utilized
Project Approved
Construction / Implementation
Original End Date
2026-03-31
Revised Completion
2028-12-31
Completed
Project is within original budget of ₹8975 Cr — no cost escalation recorded.
Expenditure stands at ₹4799 Cr, which is 53.5% of the revised project cost.
Remaining budget: ₹4176 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.