Original Cost
₹2595 Cr
Baseline estimate
Revised Cost
₹3071 Cr
Latest approved cost
Expenditure
₹4155 Cr
Spent to date
Utilization
135.3%
Of revised budget
Cost Status
+18.3%
+₹476 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹4155 Cr
Remaining
₹0 Cr
Total
₹3071 Cr
Original Cost
₹2595 Cr
Revised Cost
₹3071 Cr
Increase
+₹476 Cr
Escalation
+18.3%
Project Approved
Construction / Implementation
Original End Date
31/01/2025
Revised Completion
30/11/2025
Completed
Cost has increased by ₹476 Cr (18.3%) from the original estimate of ₹2595 Cr.
Expenditure stands at ₹4155 Cr, which is 135.3% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.