RailwaysIPM · Central Project +58.0% overrun#400273

Tarakeswar-Bishnupur with extension upto Dhaniakhali, Arambagh-Irphala, Irphala-Ghatal 11.2 km, Arambagh-Champadanga 23.3 km & Bishnupur-Uparsol 31.8 km and new material modification for Mynapur-Kamarpukur via Birsha 19 km

Ministry of RailwaysWest Bengal
Revised Cost: ₹1879 CrUtilization: 85.6%Overrun: +₹690 Cr

Original Cost

₹1189 Cr

Baseline estimate

+58% overrun

Revised Cost

₹1879 Cr

Latest approved cost

Expenditure

₹1608 Cr

Spent to date

Utilization

85.6%

Of revised budget

Escalated

Cost Status

+58.0%

+₹690 Cr increase

Remaining

₹271 Cr

Budget left

Budget Utilization

85.6%
0%25%50%75%100%

Spent

₹1608 Cr

Remaining

₹271 Cr

Total

₹1879 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1189 Cr

Revised Cost

₹1879 Cr

Increase

+₹690 Cr

Escalation

+58.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2019

Revised Completion

28/02/2026

Completed

Project Details

Project Code400273
SectorRailways
MinistryMinistry of Railways
StateWest Bengal
Data Month2026-07

Financial Summary

Original Cost₹1189 Cr
Revised Cost₹1879 Cr
Expenditure₹1608 Cr
Original End Date31/03/2019
Revised Date28/02/2026

Project Intelligence

Cost has increased by ₹690 Cr (58.0%) from the original estimate of ₹1189 Cr.

Expenditure stands at ₹1608 Cr, which is 85.6% of the revised project cost.

Remaining budget: ₹271 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Tarakeswar-Bishnupur with extension upto Dhaniakhali, Arambagh-Irphala, Irphala-Ghatal 11.2 km, Arambagh-Champadanga 23.3 km & Bishnupur-Uparsol 31.8 km and new material modification for Mynapur-Kamarpukur via Birsha 19 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1189.00 Cr, later revised to ₹1878.82 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Tarakeswar-Bishnupur with extension upto Dhaniakhali, Arambagh-Irphala, Irphala-"?
Tarakeswar-Bishnupur with extension upto Dhaniakhali, Arambagh-Irphala, Irphala-Ghatal 11.2 km, Arambagh-Champadanga 23.3 km & Bishnupur-Uparsol 31.8 km and new material modification for Mynapur-Kamarpukur via Birsha 19 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: West Bengal. Original cost: ₹1189 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1189 Cr and has been revised to ₹1879 Cr — a cost overrun of +58%. Expenditure to date: ₹1608 Cr (85.6% of revised cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
Tarakeswar-Bishnupur with extension upto Dhaniakhali, Aramba is under the Ministry of Railways in the Railways sector. Project code: 400273. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Tarakeswar-Bishnupur with extension upto Dhaniakhali, Aramba is one of several Bihar projects tracked under the Railways sector on the IPM system.