Original Cost
₹665 Cr
Baseline estimate
Revised Cost
₹665 Cr
Latest approved cost
Expenditure
₹23 Cr
Spent to date
Utilization
3.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹642 Cr
Budget left
Spent
₹23 Cr
Remaining
₹642 Cr
Total
₹665 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2028
Revised Completion
Completed
Project is within original budget of ₹665 Cr — no cost escalation recorded.
Expenditure stands at ₹23 Cr, which is 3.5% of the revised project cost.
Remaining budget: ₹642 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Metals & Mining. Ministry: Ministry of Mines.