Original Cost
₹2408 Cr
Baseline estimate
Revised Cost
₹2408 Cr
Latest approved cost
Expenditure
₹2779 Cr
Spent to date
Utilization
115.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹0 Cr
Budget left
Spent
₹2779 Cr
Remaining
₹0 Cr
Total
₹2408 Cr
Project Approved
Construction / Implementation
Original End Date
30/06/2023
Revised Completion
30/06/2027
Completed
Project is within original budget of ₹2408 Cr — no cost escalation recorded.
Expenditure stands at ₹2779 Cr, which is 115.4% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.