Original Cost
₹3808 Cr
Baseline estimate
Revised Cost
₹9580 Cr
Latest approved cost
Expenditure
₹6040 Cr
Spent to date
Utilization
63.1%
Of revised budget
Cost Status
+151.6%
+₹5772 Cr increase
Remaining
₹3539 Cr
Budget left
Spent
₹6040 Cr
Remaining
₹3539 Cr
Total
₹9580 Cr
Original Cost
₹3808 Cr
Revised Cost
₹9580 Cr
Increase
+₹5772 Cr
Escalation
+151.6%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/03/2026
Completed
Cost has increased by ₹5772 Cr (151.6%) from the original estimate of ₹3808 Cr.
Expenditure stands at ₹6040 Cr, which is 63.1% of the revised project cost.
Remaining budget: ₹3539 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.