Strengthening, Widening & Up-gradation of newly declared NH-761 from NH-61Junction-BelheAlkutiDevibhoyareNighojShirur, from Design chainage Km 0.000 to Km 37.970 from Single/Intermediate/2L to 2LPS in the State of Maharashtra on EPC Mode Length 37.970 Km
Original Cost
₹386 Cr
Baseline estimate
Revised Cost
₹386 Cr
Latest approved cost
Expenditure
₹115 Cr
Spent to date
Utilization
29.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹271 Cr
Budget left
Budget Utilization
29.7%Spent
₹115 Cr
Remaining
₹271 Cr
Total
₹386 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
27/09/2026
Revised Completion
27/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹386 Cr — no cost escalation recorded.
Expenditure stands at ₹115 Cr, which is 29.7% of the revised project cost.
Remaining budget: ₹271 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Strengthening, Widening & Up-gradation of newly declared NH-761 from NH-61Junction-BelheAlkutiDevibhoyareNighojShirur, from Design chainage Km 0.000 to Km 37.970 from Single/Intermediate/2L to 2LPS in the State of Maharashtra on EPC Mode Length 37.970 Km is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹386.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Strengthening, Widening & Up-gradation of newly declared NH-761 from NH-61Juncti"?
- Strengthening, Widening & Up-gradation of newly declared NH-761 from NH-61Junction-BelheAlkutiDevibhoyareNighojShirur, from Design chainage Km 0.000 to Km 37.970 from Single/Intermediate/2L to 2LPS in the State of Maharashtra on EPC Mode Length 37.970 Km is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹386 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹386 Cr has not been significantly revised. Expenditure: ₹115 Cr (29.7% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Strengthening, Widening & Up-gradation of newly declared NH- is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618061. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Strengthening, Widening & Up-gradation of newly declared NH- is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.