Original Cost
₹386 Cr
Baseline estimate
Revised Cost
₹386 Cr
Latest approved cost
Expenditure
₹31 Cr
Spent to date
Utilization
8.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹355 Cr
Budget left
Spent
₹31 Cr
Remaining
₹355 Cr
Total
₹386 Cr
Project Approved
Construction / Implementation
Original End Date
27/09/2026
Revised Completion
27/09/2026
Completed
Project is within original budget of ₹386 Cr — no cost escalation recorded.
Expenditure stands at ₹31 Cr, which is 8.0% of the revised project cost.
Remaining budget: ₹355 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.