Roads & HighwaysIPM · Central Project#617973

Strengthening and widening of existing 2 lane road to two lane paved shoulder from km 7.750 to 26.542 & km. 32.093 to 45.786 of NH-130 on EPC mode in the state of chhattisgarh.job No. 130-CG-2017-18-348

Ministry of Road Transport & HighwaysChhattisgarh
Revised Cost: ₹189 CrUtilization: 54.3%

Original Cost

₹189 Cr

Baseline estimate

On budget

Revised Cost

₹189 Cr

Latest approved cost

Expenditure

₹103 Cr

Spent to date

Utilization

54.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹86 Cr

Budget left

Budget Utilization

54.3%
0%25%50%75%100%

Spent

₹103 Cr

Remaining

₹86 Cr

Total

₹189 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

24/11/2020

Revised Completion

28/02/2026

Completed

Project Details

Project Code617973
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateChhattisgarh
Data Month2026-05

Financial Summary

Original Cost₹189 Cr
Revised Cost₹189 Cr
Expenditure₹103 Cr
Original End Date24/11/2020
Revised Date28/02/2026

Project Intelligence

Project is within original budget of ₹189 Cr — no cost escalation recorded.

Expenditure stands at ₹103 Cr, which is 54.3% of the revised project cost.

Remaining budget: ₹86 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Strengthening and widening of existing 2 lane road to two lane paved shoulder from km 7.750 to 26.542 & km. 32.093 to 45.786 of NH-130 on EPC mode in the state of chhattisgarh.job No. 130-CG-2017-18-348 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹189.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Strengthening and widening of existing 2 lane road to two lane paved shoulder fr"?
Strengthening and widening of existing 2 lane road to two lane paved shoulder from km 7.750 to 26.542 & km. 32.093 to 45.786 of NH-130 on EPC mode in the state of chhattisgarh.job No. 130-CG-2017-18-348 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Chhattisgarh. Original cost: ₹189 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹189 Cr has not been significantly revised. Expenditure: ₹103 Cr (54.3% of cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Strengthening and widening of existing 2 lane road to two la is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617973. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Strengthening and widening of existing 2 lane road to two la is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.