Original Cost
₹2641 Cr
Baseline estimate
Revised Cost
₹3309 Cr
Latest approved cost
Expenditure
₹932 Cr
Spent to date
Utilization
28.2%
Of revised budget
Cost Status
+25.3%
+₹668 Cr increase
Remaining
₹2377 Cr
Budget left
Spent
₹932 Cr
Remaining
₹2377 Cr
Total
₹3309 Cr
Original Cost
₹2641 Cr
Revised Cost
₹3309 Cr
Increase
+₹668 Cr
Escalation
+25.3%
Project Approved
Construction / Implementation
Original End Date
29/03/2025
Revised Completion
30/06/2027
Completed
Cost has increased by ₹668 Cr (25.3%) from the original estimate of ₹2641 Cr.
Expenditure stands at ₹932 Cr, which is 28.2% of the revised project cost.
Remaining budget: ₹2377 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.