Water ResourcesIPM · Central Project +29.1% overrun#400102

Sri Ram Sagar Project Stage - II

Department of Water Resources, River Development & GRTelangana
Revised Cost: ₹950 CrUtilization: 102.3%Overrun: +₹214 Cr

Original Cost

₹736 Cr

Baseline estimate

+29% overrun

Revised Cost

₹950 Cr

Latest approved cost

Expenditure

₹971 Cr

Spent to date

Utilization

102.3%

Of revised budget

Escalated

Cost Status

+29.1%

+₹214 Cr increase

Remaining

₹0 Cr

Budget left

Budget Utilization

102.3%
0%25%50%75%100%

Spent

₹971 Cr

Remaining

₹0 Cr

Total

₹950 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹736 Cr

Revised Cost

₹950 Cr

Increase

+₹214 Cr

Escalation

+29.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2019

Revised Completion

31/12/2025

Completed

Project Details

Project Code400102
SectorWater Resources
MinistryDepartment of Water Resources, River Development & GR
StateTelangana
Data Month2026-08

Financial Summary

Original Cost₹736 Cr
Revised Cost₹950 Cr
Expenditure₹971 Cr
Original End Date31/12/2019
Revised Date31/12/2025

Project Intelligence

Cost has increased by ₹214 Cr (29.1%) from the original estimate of ₹736 Cr.

Expenditure stands at ₹971 Cr, which is 102.3% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.

Sri Ram Sagar Project Stage - II is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹736.00 Cr, later revised to ₹949.87 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Sri Ram Sagar Project Stage - II"?
Sri Ram Sagar Project Stage - II is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Telangana. Original cost: ₹736 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹736 Cr and has been revised to ₹950 Cr — a cost overrun of +29.1%. Expenditure to date: ₹971 Cr (102.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Sri Ram Sagar Project Stage - II is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 400102. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Sri Ram Sagar Project Stage - II is one of several Bihar projects tracked under the Water Resources sector on the IPM system.