Original Cost
₹736 Cr
Baseline estimate
Revised Cost
₹950 Cr
Latest approved cost
Expenditure
₹971 Cr
Spent to date
Utilization
102.3%
Of revised budget
Cost Status
+29.1%
+₹214 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹971 Cr
Remaining
₹0 Cr
Total
₹950 Cr
Original Cost
₹736 Cr
Revised Cost
₹950 Cr
Increase
+₹214 Cr
Escalation
+29.1%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/12/2025
Completed
Cost has increased by ₹214 Cr (29.1%) from the original estimate of ₹736 Cr.
Expenditure stands at ₹971 Cr, which is 102.3% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.