South Central Railway- 3rd line between Gudur-Renigunta stations 83.17 km PB34/CR/2023-24

Ministry of RailwaysAndhra Pradesh
Revised Cost: ₹877 CrUtilization: 6.1%

Original Cost

₹877 Cr

Baseline estimate

On budget

Revised Cost

₹877 Cr

Latest approved cost

Expenditure

₹53 Cr

Spent to date

Utilization

6.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹824 Cr

Budget left

Budget Utilization

6.1%
0%25%50%75%100%

Spent

₹53 Cr

Remaining

₹824 Cr

Total

₹877 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2027

Revised Completion

Completed

Project Details

Project Code617216
SectorRailways
MinistryMinistry of Railways
StateAndhra Pradesh
Data Month2026-08

Financial Summary

Original Cost₹877 Cr
Revised Cost₹877 Cr
Expenditure₹53 Cr
Original End Date31/03/2027
Revised DateN/A

Project Intelligence

Project is within original budget of ₹877 Cr — no cost escalation recorded.

Expenditure stands at ₹53 Cr, which is 6.1% of the revised project cost.

Remaining budget: ₹824 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

South Central Railway- 3rd line between Gudur-Renigunta stations 83.17 km PB34/CR/2023-24 is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹877.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "South Central Railway- 3rd line between Gudur-Renigunta stations 83.17 km PB34/C"?
South Central Railway- 3rd line between Gudur-Renigunta stations 83.17 km PB34/CR/2023-24 is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Andhra Pradesh. Original cost: ₹877 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹877 Cr has not been significantly revised. Expenditure: ₹53 Cr (6.1% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
South Central Railway- 3rd line between Gudur-Renigunta stat is under the Ministry of Railways in the Railways sector. Project code: 617216. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. South Central Railway- 3rd line between Gudur-Renigunta stat is one of several Bihar projects tracked under the Railways sector on the IPM system.