RailwaysIPM · Central Project +82.1% overrun#705735

Solapur-Osmanabad - New line via Tuljapur 84.44 km umbrella work PB23/2018-19/NR

Ministry of RailwaysMaharashtra
Revised Cost: ₹1648 CrUtilization: 74.8%Overrun: +₹743 Cr

Original Cost

₹905 Cr

Baseline estimate

+82% overrun

Revised Cost

₹1648 Cr

Latest approved cost

Expenditure

₹1233 Cr

Spent to date

Utilization

74.8%

Of revised budget

Escalated

Cost Status

+82.1%

+₹743 Cr increase

Remaining

₹415 Cr

Budget left

Budget Utilization

74.8%
0%25%50%75%100%

Spent

₹1233 Cr

Remaining

₹415 Cr

Total

₹1648 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹905 Cr

Revised Cost

₹1648 Cr

Increase

+₹743 Cr

Escalation

+82.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2027

Revised Completion

28/03/2028

Completed

Project Details

Project Code705735
SectorRailways
MinistryMinistry of Railways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹905 Cr
Revised Cost₹1648 Cr
Expenditure₹1233 Cr
Original End Date31/03/2027
Revised Date28/03/2028

Project Intelligence

Cost has increased by ₹743 Cr (82.1%) from the original estimate of ₹905 Cr.

Expenditure stands at ₹1233 Cr, which is 74.8% of the revised project cost.

Remaining budget: ₹415 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Solapur-Osmanabad - New line via Tuljapur 84.44 km umbrella work PB23/2018-19/NR is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹905.00 Cr, later revised to ₹1647.87 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Solapur-Osmanabad - New line via Tuljapur 84.44 km umbrella work PB23/2018-19/NR"?
Solapur-Osmanabad - New line via Tuljapur 84.44 km umbrella work PB23/2018-19/NR is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹905 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹905 Cr and has been revised to ₹1648 Cr — a cost overrun of +82.1%. Expenditure to date: ₹1233 Cr (74.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Solapur-Osmanabad - New line via Tuljapur 84.44 km umbrella is under the Ministry of Railways in the Railways sector. Project code: 705735. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Solapur-Osmanabad - New line via Tuljapur 84.44 km umbrella is one of several Bihar projects tracked under the Railways sector on the IPM system.