Roads & HighwaysIPM · Central Project +72.3% overrun#619003

Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.139 to Km.129.05

Ministry of Road Transport & HighwaysHimachal Pradesh
Revised Cost: ₹1520 CrUtilization: 88.7%Overrun: +₹638 Cr

Original Cost

₹882 Cr

Baseline estimate

+72% overrun

Revised Cost

₹1520 Cr

Latest approved cost

Expenditure

₹1348 Cr

Spent to date

Utilization

88.7%

Of revised budget

Escalated

Cost Status

+72.3%

+₹638 Cr increase

Remaining

₹171 Cr

Budget left

Budget Utilization

88.7%
0%25%50%75%100%

Spent

₹1348 Cr

Remaining

₹171 Cr

Total

₹1520 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹882 Cr

Revised Cost

₹1520 Cr

Increase

+₹638 Cr

Escalation

+72.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/05/2021

Revised Completion

16/11/2026

Completed

Project Details

Project Code619003
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateHimachal Pradesh
Data Month2026-08

Financial Summary

Original Cost₹882 Cr
Revised Cost₹1520 Cr
Expenditure₹1348 Cr
Original End Date06/05/2021
Revised Date16/11/2026

Project Intelligence

Cost has increased by ₹638 Cr (72.3%) from the original estimate of ₹882 Cr.

Expenditure stands at ₹1348 Cr, which is 88.7% of the revised project cost.

Remaining budget: ₹171 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.139 to Km.129.05 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹882.00 Cr, later revised to ₹1519.53 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.139 to Km.129.05"?
Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.139 to Km.129.05 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹882 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹882 Cr and has been revised to ₹1520 Cr — a cost overrun of +72.3%. Expenditure to date: ₹1348 Cr (88.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.1 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619003. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.1 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.