Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.139 to Km.129.05
Original Cost
₹882 Cr
Baseline estimate
Revised Cost
₹1520 Cr
Latest approved cost
Expenditure
₹1348 Cr
Spent to date
Utilization
88.7%
Of revised budget
Cost Status
+72.3%
+₹638 Cr increase
Remaining
₹171 Cr
Budget left
Budget Utilization
88.7%Spent
₹1348 Cr
Remaining
₹171 Cr
Total
₹1520 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹882 Cr
Revised Cost
₹1520 Cr
Increase
+₹638 Cr
Escalation
+72.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
06/05/2021
Revised Completion
16/11/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹638 Cr (72.3%) from the original estimate of ₹882 Cr.
Expenditure stands at ₹1348 Cr, which is 88.7% of the revised project cost.
Remaining budget: ₹171 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.139 to Km.129.05 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹882.00 Cr, later revised to ₹1519.53 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.139 to Km.129.05"?
- Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.139 to Km.129.05 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹882 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹882 Cr and has been revised to ₹1520 Cr — a cost overrun of +72.3%. Expenditure to date: ₹1348 Cr (88.7% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.1 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619003. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.1 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.