Six Laning of KT/KL Border Thalapaddy -Chengala from Km. 17.200 to Km. 57.20
Original Cost
₹1981 Cr
Baseline estimate
Revised Cost
₹2681 Cr
Latest approved cost
Expenditure
₹1796 Cr
Spent to date
Utilization
67.0%
Of revised budget
Cost Status
+35.4%
+₹700 Cr increase
Remaining
₹886 Cr
Budget left
Budget Utilization
67.0%Spent
₹1796 Cr
Remaining
₹886 Cr
Total
₹2681 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1981 Cr
Revised Cost
₹2681 Cr
Increase
+₹700 Cr
Escalation
+35.4%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
15/05/2024
Revised Completion
03/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹700 Cr (35.4%) from the original estimate of ₹1981 Cr.
Expenditure stands at ₹1796 Cr, which is 67.0% of the revised project cost.
Remaining budget: ₹886 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Six Laning of KT/KL Border Thalapaddy -Chengala from Km. 17.200 to Km. 57.20 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1981.00 Cr, later revised to ₹2681.48 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Six Laning of KT/KL Border Thalapaddy -Chengala from Km. 17.200 to Km. 57.20"?
- Six Laning of KT/KL Border Thalapaddy -Chengala from Km. 17.200 to Km. 57.20 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Kerala. Original cost: ₹1981 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1981 Cr and has been revised to ₹2681 Cr — a cost overrun of +35.4%. Expenditure to date: ₹1796 Cr (67.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Six Laning of KT/KL Border Thalapaddy -Chengala from Km. 17. is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619205. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Six Laning of KT/KL Border Thalapaddy -Chengala from Km. 17. is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.