Original Cost
₹1981 Cr
Baseline estimate
Revised Cost
₹2681 Cr
Latest approved cost
Expenditure
₹1061 Cr
Spent to date
Utilization
39.6%
Of revised budget
Cost Status
+35.4%
+₹700 Cr increase
Remaining
₹1621 Cr
Budget left
Spent
₹1061 Cr
Remaining
₹1621 Cr
Total
₹2681 Cr
Original Cost
₹1981 Cr
Revised Cost
₹2681 Cr
Increase
+₹700 Cr
Escalation
+35.4%
Project Approved
Construction / Implementation
Original End Date
15/05/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹700 Cr (35.4%) from the original estimate of ₹1981 Cr.
Expenditure stands at ₹1061 Cr, which is 39.6% of the revised project cost.
Remaining budget: ₹1621 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.