of NH-2 from km 249.525 to km 320.810
Original Cost
₹1773 Cr
Baseline estimate
Revised Cost
₹1689 Cr
Latest approved cost
Expenditure
₹563 Cr
Spent to date
Utilization
33.3%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹1126 Cr
Budget left
Spent
₹563 Cr
Remaining
₹1126 Cr
Total
₹1689 Cr
33.3%
Utilized
Project Approved
Construction / Implementation
Original End Date
2021-11-26
Revised Completion
2026-12-31
Completed
Project is within original budget of ₹1773 Cr — no cost escalation recorded.
Expenditure stands at ₹563 Cr, which is 33.3% of the revised project cost.
Remaining budget: ₹1126 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.