Roads & HighwaysIPM · Central Project#619078

Six Laning of Bihar - Jharkhand Border Chordaha - Gorhar section of NH-2 from km 249.525 to km 320.810

Ministry of Road Transport & HighwaysJharkhand
Revised Cost: ₹1689 CrUtilization: 76.5%

Original Cost

₹1773 Cr

Baseline estimate

On budget

Revised Cost

₹1689 Cr

Latest approved cost

Expenditure

₹1293 Cr

Spent to date

Utilization

76.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹397 Cr

Budget left

Budget Utilization

76.5%
0%25%50%75%100%

Spent

₹1293 Cr

Remaining

₹397 Cr

Total

₹1689 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

26/11/2021

Revised Completion

31/12/2026

Completed

Project Details

Project Code619078
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹1773 Cr
Revised Cost₹1689 Cr
Expenditure₹1293 Cr
Original End Date26/11/2021
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹1773 Cr — no cost escalation recorded.

Expenditure stands at ₹1293 Cr, which is 76.5% of the revised project cost.

Remaining budget: ₹397 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Six Laning of Bihar - Jharkhand Border Chordaha - Gorhar section of NH-2 from km 249.525 to km 320.810 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1773.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Six Laning of Bihar - Jharkhand Border Chordaha - Gorhar section of NH-2 from km"?
Six Laning of Bihar - Jharkhand Border Chordaha - Gorhar section of NH-2 from km 249.525 to km 320.810 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹1773 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1773 Cr and has been revised to ₹1689 Cr — a cost overrun of -4.7%. Expenditure to date: ₹1293 Cr (76.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Six Laning of Bihar - Jharkhand Border Chordaha - Gorhar sec is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619078. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Six Laning of Bihar - Jharkhand Border Chordaha - Gorhar sec is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.